Five-Year Capital Road Improvement Plan for the Highway Department
Every year the Town Board passes a resolution that outlines the five-year plan for highway capital improvements. The rolling plan is reviewed, updated and re-adopted annually. The text of the 2020 May resolution #30 is shown below as recorded in the minutes from the Town Board meeting of May 11, 2020.
2021
2022
2025
Every year the Town Board passes a resolution that outlines the five-year plan for highway capital improvements. The rolling plan is reviewed, updated and re-adopted annually. The text of the 2020 May resolution #30 is shown below as recorded in the minutes from the Town Board meeting of May 11, 2020.
2021
- Middle Road 1.16 miles from Curtis Road south to Burch Hill Road – Re-grind & profile and surface with a single shot of oil and stone.
- N. Middle Road 1.1 miles from Curtis Road north to Richmond town line – Re-grind & profile and surface with a single shot of oil and stone.
- Johnson Hill Road 0.7 miles from Canadice Lake Road east to S. Old Bald Hill Road – Surface treat with a single shot of oil & stone.
- Jersey Hill Road 0.73 miles from County Road 37 east to County Road 36 - Surface treat with a single shot of oil and stone.
2022
- Lawrence Hill Road North from Lawrence Hill Road West to Purcell Hill Road, 0.96 miles – Re-grind & profile; reconstruct shoulders and surface treat with oil and stone.
- Lawrence Hill Road West from Lawrence Hill Road North to NYS Rt 15A, 0.51 miles – Re-grind & profile, reconstruct shoulders and surface treat with oil and stone.
- Cratsley Hill Road 0.75 miles from County Road 37 to Bus Turn around – Replace cross culverts, re-profile road, reconstruct shoulders and surface with oil and stone.
- Tibbals Road 1.07 miles from Canadice Hill Road east to Ross Road – Re-profile road, reconstruct shoulders and surface treat with a single shot of oil and stone.
2025
- Canadice Hill Road 2.36 miles from Ross Road south to Tibbals Road – Cut in weeps as necessary, re-profile/grind road with crusher run and calcium, surface treat with two shots of oil and stone.