Five-Year Capital Road Improvement Plan for the Highway Department
Every year the Town Board passes a resolution that outlines the five-year plan for highway capital improvements. The rolling plan is reviewed, updated and re-adopted annually.
2022
2025
2026
Every year the Town Board passes a resolution that outlines the five-year plan for highway capital improvements. The rolling plan is reviewed, updated and re-adopted annually.
2022
- Lawrence Hill Road North from Lawrence Hill Road West to Purcell Hill Road, 0.96 miles – Re-grind & profile; reconstruct shoulders and surface treat with oil and stone.
- Lawrence Hill Road West from Lawrence Hill Road North to NYS Rt 15A, 0.51 miles – Re-grind & profile, reconstruct shoulders and surface treat with oil and stone.
- Cratsley Hill Road 0.75 miles from County Road 37 to Bus Turn around – Replace cross culverts, re-profile road, reconstruct shoulders and surface with oil and stone.
- Tibbals Road 1.07 miles from Canadice Hill Road east to Ross Road – Re-profile road, reconstruct shoulders and surface treat with a single shot of oil and stone.
2025
- Canadice Hill Road 2.36 miles from Ross Road south to Tibbals Road – Cut in weeps as necessary, re-profile/grind road with crusher run and calcium, surface treat with two shots of oil and stone.
2026
- Lawrence Hill Road N/S 1.28 miles from Purcell Hill Road to the dead end. Re-profile, cold mix pave and surface treat with a single shot of oil and stone.
- Lawrence Hill Road E/W .51 of a mile from State Route 15A to Lawrence Hill Road N. Re-profile, cold mix pave and surface treat with a single shot of oil and stone.